This is a decision checklist, not a substitute for the full legal framework. For the complete society-level guide, read Development Agreement for Society Redevelopment in Maharashtra: Complete Guide. For member-specific accommodation rights, see PAAA in Redevelopment.
Before the 12 clauses: one legal point matters
Maharashtra's 4 July 2019 redevelopment directions under Section 79A contain detailed guidance on the agreement with the selected developer, including project duration, a 20% project-cost bank-guarantee guideline, temporary accommodation/rent, registration of the Development Agreement and PAAA, RERA carpet area, non-transferability of development rights and pre-vacating protections.
However, the Bombay High Court's 24 August 2026 decision in Dudhsagar Co-operative Housing Society Ltd. v. Mukund Vaman Patankar & Others described the 2019 GR as providing standard guidelines and referred to earlier authority treating it as directory rather than mandatory in the sense that every procedural lapse automatically invalidates redevelopment.
Clause 1 — Development rights: what exactly is the society giving away?
This is the foundation clause. It should identify the property, the rights granted to the developer and the limits on those rights.
Members should ask:
- Which CTS/survey numbers, buildings and land parcels are covered?
- Is the grant exclusive, and for how long?
- Which existing and future FSI/FAR/TDR or incentive development rights can the developer use?
- Can adjoining land be amalgamated?
- Who owns unused development potential after completion?
- Can the developer create third-party rights over common areas?
- What happens to these rights on termination?
Clause 2 — Member entitlement: RERA carpet area, flat allocation and specifications
The 2019 directions say the agreement should clearly mention the carpet area payable under RERA. The DA should therefore set the society-level entitlement framework in measurable terms.
| Item | What the clause should answer |
|---|---|
| Replacement area | Exact free RERA carpet area or the precise formula for each member category |
| Additional area | Free versus paid area shown separately, with rate/tax/payment terms |
| Flat allocation | Wing, floor, flat number or a transparent allocation/lottery process |
| Parking | Type and allocation mechanism consistent with applicable law and approvals |
| Specifications | Written schedule for flooring, windows, doors, sanitaryware, electrical points, lifts and common amenities |
| Plan changes | What happens if the sanctioned plan requires a material change to the promised unit |
Each member's PAAA should reconcile with this framework. If the DA says 700 sq ft RERA carpet and the PAAA says 680 sq ft, that is not a drafting detail—it is a commercial discrepancy that should be resolved before signing.
Clause 3 — Transit rent, deposit, escalation and delayed possession
A good rent clause is a payment system, not merely a monthly number.
Check:
- monthly rent amount;
- when rent starts;
- whether it is paid monthly or in advance;
- deposit and brokerage;
- shifting charges;
- annual escalation and exact anniversary date;
- payment method and evidence;
- interest/default consequence for late payment;
- whether rent continues through extensions and disputes;
- the exact event that stops rent.
“Rent stops when possession is offered” is risky if “offer” is not tied to lawful occupancy approval, completed specifications and actual ability to occupy.
Clause 4 — Bank guarantee and performance security
The 2019 directions include a guideline for a bank guarantee equal to 20% of the total redevelopment project cost. The number alone is not enough.
Review:
- what “total project cost” means for calculating the guarantee;
- issuing bank and acceptable bank category;
- beneficiary;
- guarantee validity;
- automatic renewal or renewal deadline;
- notice before expiry;
- events allowing invocation;
- whether invocation is on demand or conditional;
- when and how the guarantee can be reduced;
- what happens if it is not renewed.
The society should keep the guarantee itself—not just a developer letter saying one has been arranged—and track expiry dates throughout construction.
Clause 5 — Pre-vacating conditions: what must exist before keys are handed over?
The 2019 guidance refers to members vacating only after legal approvals are obtained and individual PAAA registration. A Mumbai project can have staged approvals, so the DA should translate that broad wording into an objective project-specific checklist.
Possible pre-vacating conditions include:
- registered Development Agreement;
- registered member PAAA;
- specified sanctioned-plan and commencement-stage approvals;
- RERA registration where legally required;
- bank guarantee/security in force;
- transit-rent advance and deposit paid;
- insurance or other agreed protections activated;
- written vacating notice and handover procedure.
For a member-level review, use the PAAA checklist before vacating.
Clause 6 — Completion date, extensions, long-stop date and delay consequences
The 2019 GR contains a guideline that, depending on project size, completion from the relevant first/foundation commencement certificate should not exceed two years and, in exceptional circumstances, three years. The DA should nevertheless define the project's actual contractual clock.
Members should be able to identify:
- the commencement trigger;
- major approval/construction milestones;
- target OC and possession date;
- permitted extension events;
- developer's notice and evidence requirements;
- maximum or long-stop completion date;
- rent and escalation during delay;
- liquidated damages, interest or other negotiated consequences;
- when repeated or prolonged delay becomes an event of default.
A RERA registration extension is a regulatory event; it should not automatically erase stronger contractual rent or delay remedies unless the DA expressly says so.
Clause 7 — Sanctioned-plan changes and member/allottee consent
Redevelopment plans can change because of authority comments, structural design, DCPR calculations or commercial revisions. The DA should separate minor technical adjustments from changes that affect member entitlements or common areas.
Where RERA applies, Section 14 requires the project to follow sanctioned plans and restricts specified alterations. It also requires prior written consent of at least two-thirds of allottees, other than the promoter, for specified other alterations or additions to sanctioned plans or common areas, subject to the Act.
The DA should create a change-control process:
- Developer proposes the change.
Reason and revised drawings are documented. - PMC/architect analyses impact.
Area, specifications, common areas, cost and schedule are compared. - Required approvals/consents are obtained.
Authority, General Body and/or allottee consent as applicable. - The record is updated.
Superseded and revised plans remain traceable, and affected PAAA/entitlement schedules are corrected if necessary.
Clause 8 — Mortgage, project finance and lender protections
Most large redevelopment projects require finance. The problem is not financing itself; it is unclear financing rights that can collide with member rehabilitation rights.
Ask the society's lawyer to explain:
- what land, development rights, receivables and sale inventory may be charged;
- whether the rehab component can be mortgaged;
- whether existing member units/replacement units are excluded;
- what lender notices and consents are required;
- how and when mortgage releases will be obtained;
- what happens if the lender enforces security;
- whether a lender may replace the developer;
- whether society consent is required for finance restructuring.
RERA Section 11 also protects an allottee's interest against certain later mortgages or charges after an agreement for sale, but the society should not use that as a substitute for project-specific mortgage restrictions.
Clause 9 — Assignment, SPV changes and change of control
The 2019 Maharashtra guidance says development rights granted to the developer should be non-transferable. RERA Section 15 separately restricts transfer or assignment of majority project rights and liabilities without prior written consent of two-thirds of allottees, excluding the promoter, and prior Authority approval where RERA applies.
The DA should cover more than a formal assignment document. It should define the treatment of:
- transfer to an SPV or affiliate;
- sale of controlling shares;
- merger or business transfer;
- joint-development arrangements;
- lender enforcement or nominee developer;
- replacement of promoter versus replacement of contractor.
Clause 10 — Specifications, quality, defects and inspection rights
Marketing brochures are not enough. Attach or incorporate a proper specification schedule.
Include:
- structural/design standards;
- flooring, doors, windows and waterproofing;
- electrical points/load and backup systems;
- plumbing and sanitaryware;
- lifts and fire/life-safety systems;
- common-area finishes;
- parking/EV commitments if agreed;
- approved-equivalent substitution process;
- PMC inspection and testing rights;
- snagging and rectification;
- warranties and O&M documentation.
For RERA-registered projects, Section 14 also provides a five-year defect-remediation framework for specified defects from possession, with a 30-day rectification obligation after notice. The DA can provide additional contractual quality protections without reducing statutory rights.
Clause 11 — Default, termination and replacement developer
The default clause should tell the society what happens before, during and after a serious failure.
| Default example | What the clause should provide |
|---|---|
| Rent default | Cure period, interest, direct-payment option, security consequences |
| Bank guarantee lapse | Mandatory renewal, immediate default/invocation rights before expiry |
| Material construction delay | Recovery plan, enhanced reporting, damages and long-stop trigger |
| Unauthorised assignment | Stop/injunction/termination rights and restoration of society control |
| Insolvency or abandonment | Site access/control, security invocation and emergency transition |
| Material plan breach | Correction process, member-consent consequences and work restrictions |
Termination should also cover the practical transition: possession/control of the site, handover of plans and approvals, RERA credentials, consultant records, treatment of purchasers and lenders, continued member rent, use of the bank guarantee and cooperation with a replacement developer.
Clause 12 — OC, possession, final handover and document closure
The final clause should define what “project complete” means.
Members should look for:
- Occupation Certificate or the required lawful occupancy approval for the relevant building/phase;
- completion of agreed unit specifications;
- essential services operating;
- snagging and rectification process;
- release of relevant mortgages/security;
- member possession letter and key handover;
- common-area and society handover;
- as-built plans, approvals, warranties and manuals;
- final accounts/dues where contractually required;
- conditions for bank-guarantee release;
- records and credentials that remain with the society after the developer exits.
The 2019 directions link allocation of redeveloped premises to receipt of the Occupation Certificate and also call for approved construction plans to be presented to the General Body for information and made available to members who request them.
The 12-clause review matrix
| # | Clause | The question members should ask |
|---|---|---|
| 1 | Development rights | What exactly are we giving the developer, for how long, and what returns on termination? |
| 2 | Member entitlement | What exact RERA carpet area, flat, parking and specifications does each member receive? |
| 3 | Transit rent | How much, when paid, how escalated and when does it stop? |
| 4 | Bank guarantee | How much security exists, when does it expire and how can the society invoke it? |
| 5 | Pre-vacating conditions | Which approvals, PAAA, payments and security must exist before keys are handed over? |
| 6 | Completion & delay | What starts the clock, what is the long-stop date and what happens if it is missed? |
| 7 | Plan changes | Which changes require PMC review, General Body approval or allottee/member consent? |
| 8 | Mortgage & finance | What can the developer mortgage and how are rehabilitation/member rights protected? |
| 9 | Assignment | Can the project, SPV or control of the developer change without society consent? |
| 10 | Quality & defects | What specification is enforceable and how are defects inspected and corrected? |
| 11 | Default & termination | How does the society protect members and replace the developer if performance fails? |
| 12 | OC & handover | What documents, approvals, releases and completed works are required for lawful possession? |
How the society should review the final draft
- Compare against the tender and final offer.
List every changed commercial term. - PMC reviews technical clauses.
Area, plans, specifications, milestones and approvals. - Independent society lawyer reviews legal clauses.
Title, rights, mortgage, security, assignment, default and dispute provisions. - Create a clause summary for members.
Do not expect every member to decode the entire agreement unaided. - Resolve inconsistencies with the PAAA.
Area, rent, possession and benefits should match. - Approve the final negotiated version through the required governance process.
Keep the approved draft/version identifiable. - Register and archive the executed document.
Keep the executed DA, annexures and subsequent amendments together.
Make every important DA clause visible after signing
Rudh Systems can organise the Development Agreement, PAAA records, member entitlements, rent ledger, bank guarantee, approvals, RERA status, PMC reports, plan revisions, milestones and amendments in one controlled redevelopment portal—so members can check whether the project is following the contract.
Frequently asked questions
What are the most important clauses in a redevelopment agreement?
For a Mumbai cooperative housing society, the highest-impact clauses normally cover development rights, member replacement entitlement, transit rent, bank guarantee and security, pre-vacating conditions, completion and delay, plan changes, project finance and mortgage rights, assignment/change of control, construction specifications and defects, default/termination and final OC/possession/handover.
Is the 20% bank guarantee mandatory in every Maharashtra redevelopment?
The 4 July 2019 redevelopment directions include a 20% of total project cost bank-guarantee guideline. The Bombay High Court has described the 2019 GR as standard or directory guidance, so the society should not rely on the guideline alone; the amount, validity, renewal, invocation and release conditions should be written into the Development Agreement.
Should transit rent terms be in the Development Agreement or only the PAAA?
They should be consistent in both. The society-level Development Agreement should establish the common rent, deposit, escalation, payment and delay framework, while the individual PAAA should record the member-specific entitlement without reducing the society-level bargain.
Can the developer change the sanctioned plans after the agreement?
The Development Agreement should create a change-control process. Where RERA applies, Section 14 restricts changes to sanctioned plans and specifications and requires consent in specified circumstances. The DA should also require PMC review and General Body/member approval where the contract or applicable law requires it.
Can a developer mortgage the redevelopment property?
Project finance can involve security, but the Development Agreement should precisely state what can be mortgaged, what cannot, lender rights, releases and protections for rehabilitation premises and society/member interests. A blanket mortgage power is a major review point.
Can the developer transfer the redevelopment project to another company?
The 2019 Maharashtra guidance states that development rights granted to the developer should be non-transferable. RERA Section 15 separately restricts transfer of majority project rights and liabilities without specified allottee consent and Authority approval where RERA applies. The DA should also address SPVs, change of control, mergers and lender enforcement.
What should happen if the developer stops paying transit rent?
The DA should define a short cure period, interest or default consequences, continued rent liability, any direct-payment mechanism, bank-guarantee invocation rights and whether repeated or prolonged non-payment becomes a termination event.
When should members vacate?
The DA should list objective pre-vacating conditions. The 2019 directions refer to legal approvals and registration of the individual PAAA before members vacate. Because projects are staged and the GR is directory guidance, the contract should state exactly which approvals, payments and securities must be in place for that project before possession is handed over.
What should the completion clause include?
It should include a defined commencement trigger, milestone dates, target OC/possession date, extension events, notice and evidence requirements, long-stop date, continued transit-rent liability during delay and contractual consequences if the long-stop date is missed.
What should members receive at final possession?
The DA should link possession to the relevant Occupation Certificate or lawful occupancy approval, completed specifications, essential services, snagging, release of relevant finance security, keys, warranties, as-built/approval documents and the society/common-area handover package.
Primary sources and further reading
- Government of Maharashtra — 4 July 2019 redevelopment directions under Section 79A, especially clause 18.
- India Code — Real Estate (Regulation and Development) Act, 2016, including Sections 11, 14, 15, 17, 18 and 19.
- Dudhsagar Co-operative Housing Society Ltd. v. Mukund Vaman Patankar & Others, Bombay High Court, 24 August 2026.
- Maharashtra Cooperation Department — 4 November 2025 circular on redevelopment NOCs.
- Rudh Systems — Development Agreement for Society Redevelopment in Maharashtra.
- Rudh Systems — PAAA Checklist Before Vacating.